In the proverbial shadow of the Naughton Power Plant, a station in Kemmerer, Wyoming, that will stop burning coal at the end ...
The Nuclear Regulatory Commission will complete its review of TerraPower's construction permit application for its Kemmerer ...
Wyoming may see its first commercial nuclear power plant a few months sooner than anticipated, but still sometime in 2030, ...
“The Natrium project is the only advanced nuclear developer to begin construction on a commercial-scale project in the U.S. The plant design features a 345 MW sodium-cooled fast reactor with a ...
The US Nuclear Regulatory Commission now expects to complete its review of TerraPower's construction licence application for ...
NVIDIA is included in the list of investors for TerraPower's latest $650 million fundraise for deploying advanced nuclear ...
TerraPower has been riding a wave of interest from hyperscalers, data center developers, and now chip designers.
Advanced nuclear reactor firm TerraPower has closed a $650 million fundraising round, with backing from Nvidia’s venture capital arm, NVentures. The company, which is developing an advanced nuclear ...
CHEYENNE – Gov. Mark Gordon returned Thursday to the site in Kemmerer where TerraPower is building its Natrium plant for a progress briefing and tour from Eric Williams, TerraPower’s executive ...
Chris Levesque, CEO of TerraPower, called into the Weekday Wake-Up on Monday, June 30 to provide an update on the ...
Nvidia backs $650m capital raise for TerraPower to develop advanced Natrium nuclear reactor founded by Bill Gates. Clean ...
TerraPower was founded in 2006 by Bill Gates and a group of like-minded visionaries, initially pursuing the ambitious traveling wave reactor concept before evolving into the current Natrium design.